323 - Yerköy Yozgat Sivas demiryoluRailway Infrastructure

Ankara Sivas very high speed line


Milestones

  • 2004
    Route survey started.
  • May 2008
    Tender for groundwork of Yerkoy-Sivas section done. Best offer is USD 839 mn (China Major Bridge Engineering – Cengiz – Limak – Kolin).
  • Sep 2012
    Offers given for Kayas-Kirikkale section (best offer is TL 675 mn TL).
  • Jan 2013
    Kolin-Cengiz-Limak-Mapa awarded for groundwork of Kirikkale -Yerkoy section (TL 398 mn).
  • Feb 2014
    Contract inked with Dogus Insaat for Elmadag viaducts.
  • Apr 2014
    Tender opened for groundwork of Kayas-Elmadag and Elmadag-Kirikkale sections.
  • Feb 2015
    Route of railway in Sivas city center changed.
  • Sep 2015
    Offers given for groundwork of Kayas-Elmadag ve Elmadag-Kirikkale sections.
  • Oct 2016
    Place of Sivas station determined.
  • Oct 2017
    Dogus is awarded for Kayaş-Yerkoy superstructure. It covers Elmadag and Kirikkale stations, rails, electrification and signalization. Target: 18 months.
  • Mar 2018
    Rail laying started in Yerkoy-Sivas section.
  • Aug 3, 2018
    Laying of 120 km of rail on Ankara-Sivas high speed line took part in the 100-days-program of new government.
  • Oct 2018
    Many “not yet started” projects suspended with New Economic Program of the government. Gebze-Sabiha Gokcen-3rd bridge-3rd  airport-Halkali, Ankara-Sivas, Ankara-Afyonkarahisar-Izmir, Sivas-Erzincan are given priority and will continue.
  • Nov 2018
    Turhan: Deadline is 2019 1Q for Marmaray, end of 2019 for Ankara-Sivas YHT, 2020 for Ankara-Usak YHT and 2021 for Usak-Izmir YHT.
  • Nov 2018
    Dogus, the contractor constructing the viaducts of Ankara-Sivas HST railway, published the video about the project: https://youtu.be/TZW3RyVy5QA
  • Dec 13, 2018
    It’s stated in 2nd 100-days action plan of Presidency that laying of rails will reach to 450 km in Ankara-Sivas HST line. That means half of the total line.
  • Apr 2019
    Sivas train station will be closed for 8-12 months for engineering works due to Ankara-Sivas high speed train project. During this time, Bostankaya station, which is 28 km away from Sivas will be used. Shuttle service will run between two stations.
Pages: 1 2

1 reply »

  1. Interesting that the Ankara-Kayaş section is to be part of the Başkentray project BUT why wasn’t any work done on this project when the Ankara Banliyö was shut long for a very long period a few years ago? A perfect opportunity wasted. Now travellers will have to be inconvnienced once again.

    Liked by 1 person

Your questions/comments

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.