Bostanci-Dudullu metro (M8)


Milestones

  • 2007
    The metro project connecting Bostanci to Umraniye is unveiled.
  • May 13, 2013
    Prequalification tender for application projects of Dudullu-Bostanci and Umraniye-Atasehir-Goztepe projects. 8 companies are selected.
  • Dec 13, 2013
    Contract inked with Geodata SpA for application project (€ 9.5 mn) of two metro lines.
  • Apr 2015
    Environmental impact analysis started. The metro line is planned to be 14.2 km long with 13 stations. It’s expected to cost TL 4.2 bn. Tender will be opened in late 2015.
  • Sep 29, 2015
    Tender for construction of metro line. 8 offers received. Best belongs to Kalyon-Kolin-Senbay (TL 559 mn).
  • Nov 20, 2015
    Kalyon-Kolin-Senbay is awarded for the construction of metro line (TL 559 mn).
  • Feb 18, 2016
    Tender for consulting and inspection. 8 offers received. Best belongs to UBM-Optim (TL 28.5 mn).
  • Feb 25, 2016
    Contact inked with Kalyon-Kolin-Senbey for the construction of metro line. Deadline is Apr 11, 2019.
  • Mar 2016
    Tumas-Arcadis is awarded the tender for consulting and inspection services (TL 31.7 mn).
  • Apr 4, 2016
    Contract for consulting and inspection services inked.
  • Jan 23, 2017
    Tunnel works started. 4 TBMs are being used.
  • Jul 26, 2017
    Tender for rolling stock of Dudullu-Bostancı and Mahmutbey-Esenyurt metros (120 cars in total).
  • Aug 22, 2017
    Hyundai Rotem is awarded for rolling stock tender of Dudullu-Bostancı and Mahmutbey-Esenyurt metro lines. Deadline is 20 months. Project is worth TL 564 mn.
  • Dec 2017
    Contract inked with Hyundai Rotem for Dudullu-Bostanci and Mahmutbey-Esenyurt metro cars.
  • Feb 2018
    Tunnel works completed.
  • Feb 2018
    Mayor stated that first phase of 9 stations (Bostanci-IMES) will be commissioned by the end of 2018, and rest in 2019.
  • Oct 2018
    Municipality presents the completion rates as 90% for Mecidiyekoy-Mahmutbey metro, 46% for Dudullu-Bostanci metro, 33% for Halic tram, %33 for Atakoy-Ikitelli metro and 4% for Goztepe-Umraniye metro.
  • Nov 3, 2018
    Landslide in Parseller station during construction.
  • Mar 2019
    The deadline is updated as 2020 by Istanbul Metropolitan Mayorship.
Pages: 1 2

Your questions/comments

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.