Project overview

  • Owner: Istanbul Metropolitan Municipality
  • Contractor:
    • Makyol-Astur-IC Ictas-Kalyon (construction + electromechanic)
    • CRRC (metro cars – 272 cars)
  • Contract date: 4/2017
  • Contract duration: 1080 days
  • Contract deadline: 3/2020
  • Contract value:
    • TL 2.4 bn (construction + electromechanic)
    • TL 2.45 bn (metro cars – 272 cars)

Route

Kirazlı-Halkalı metrosu (M1B)
Kirazli-Halkali metro (M1B) route

Stops/connections

Kirazlı (Bakırköy-Kirazlı-Başakşehir/Olimpiyat Parkı metro) – Barbaros – Malazgirt – Mimar Sinan (Halkalı-İstanbul Airport metro) – Fatih – Halkalı Merkez – Hastane – Toplu Konut – Yarımburgaz – Halkalı (Marmaray)

Project details

This line will be extension of Yenikapi-Kirazli metro line. Rolling stock will be driverless. Yenikapi-Kirazli section will be modernized as driverless as well.

There’ll be 9 statitions, 6 of which will be underground, 2 will be partially underground and 1 will be on viaduct.

  • Line length: 9.7 km
  • Travel time: 15 min

Cover photo: İstanbul Büyükşehir Belediyesi ©

You?

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s