The scope, route,stops and history of Kocaeli’s first tram line:
Project overview
- Owner: Kocaeli Metropolitan Municipality
- Phases:
- Otogar-Sekapark
- Sekapark-Plajyolu
- Contractor:
- 1st phase: Gülermak
- 2nd phase: Emre Ray Enerji
- Rolling stock: Durmazlar
- Contract date:
- 1st phase: 8/2015
- 2nd phase: 2/2018
- Contract duration:
- 1st phase: 550 days
- 2nd phase: 540 days
- Contract deadline:
- 1st phase: 2/2017
- 2nd phase: 8/2019
- Contract value:
- 1st phase: TL 114 mn
- 2nd phase: TL 21 mn
- Rolling stock (12 sets): € 19.7 mn
- Rolling stock (6 sets): TL 45 mn
- Commission date: 1st phase: Jun 16, 2017
Route

Stops/connections
Otogar – Yahya Kaptan – Yenisehir – Mehmet Ali Pasa – Dogu Kisla – Milli İrade Meydani – Fuar – Yeni Cuma – Fevziye – Gar – Seka Park – Seka Devlet Hastanesi – Kongre Merkezi – Okullar Bölgesi – Plajyolu
Project details
The 7.5-km-long tram line connecting Otogar (main bus station) to Seka Park, and 2.2 km extension to Plajyolu project.
- Line length: 7.5 + 2.2 km
Targets
- 10k daily ridership in the beginning, 40k in 2020
Rolling Stock
Durmazlar (12 sets for 1st phase, 6 sets for 2nd phase)
Ridership
- 3.6 mn (2017, 5 months)
- 6.5 mn (2018, 9 months)