Levent Hisarustu Metro

13 New Metro Lines for Istanbul

Istanbul Metropolitan Mayor Mr Topbas gave details of soon-to-start urban rail construction works in Istanbul.

In addition to 4 lines of stanbul Metropolitan Municipality (IBB) and 3 lines of Transport Ministry, construction works will start on 13 new lines until the end of 2016.

The lines which are currently under construction or will start until the end of 2016 are as follows:

Lines Under Construction  (by IBB)

  1. Uskudar-Umraniye-Cekmekoy-Sancaktepe Metro : 20 km. Construction works started in 2012. Planned to be completed in 2016. Official Website
  2. Kartal-Kaynarca Metro : 4 km. Construction works started in 2013. Extension of Kadikoy-Kartal metro line. Planned to be completed in 2016. Official Website
  3. Mecidiyekoy-Mahmutbey Metro : 18 km. Construction works started in 2014. Planned to be completed in 2017. Officiales Website
  4. Kabatas-Mecidiyekoy Metro :5 km. Construction works started in 2015. Planned to be completed in 2019.

Lines Under Construction  (by Transport Ministry)

  1. Marmaray :7 km. 13.6 of 76.3 km is opened. Suburban lines are going to be completed. Construction works have stopped. Official Website
  2. Kaynarca-Sabiha Gokcen Metro :4 km. Will be connected to Kadıkoy-Kaynarca metro. Construction works started in August 2015.
  3. Bakırkoy (IDO)-Bagcilar (Kirazli) Metro : 9 km. Construction works started in 2015. Planned to be completed in 2018.

Announced to Start in 2015 (by IBB)

  1. Atakoy-Ikitelli Metro : 13 km. Tender and contract process have been completed. Construction works will start this month (Nov 2015). Completion is planned as 2019.
  2. Bostanci-Dudullu Metro :3 km. Tender and contract process have been completed. Construction works will start this month (Nov 2015). Completion is planned as 2019.

Announced to Start in 2016 (by IBB)

  1. Goztepe-Atasehir-Umraniye Metro : 13 km. Completion is planned as after 2019.
  2. Cekmekoy-Sultanbeyli Metro : 9 km. Completion is planned as 2019.
  3. Cekmekoy-Tasdelen-Yenidogan Metro : 7 km. Completion is planned as 2019.
  4. Kaynarca-Tuzla Metro : 8 km. Completion is planned as 2019.
  5. Pendik -Kaynarca Metro : 2 km. Completion is planned as 2019.
  6. Bagcilar (Kirazli)-Halkali Metro : 7 km. Completion is planned as 2019..
  7. Basaksehir-Kayasehir Metro : 7 km. Completion is planned as 2018.
  8. Mahmutbey-Bahcesehir Metro : 8 km. Completion is planned as 2019.
  9. Eminonu-Alibeykoy Tram : 12 km. Completion is planned as after 2019.

Announced to Start in 2016 (by Transport Ministry)

  1. Yenikapi-Incirli Metro : 7 km. Extension of Bakirkoy-Beylikduzu Metro to Yenikapi. Completion is planned as 2018.
  2. Incirli-Sefakoy Metro : 2 km. First phase of 25-km-long Incirli-Beylikduzu metro.

By the end of 2016, the lines under construction will reach to 200 km. The unit construction cost in Istanbul metros is TL 100mn/km. Most of these lines are planned to be completed by 2019. These mean that Istanbul will need TL 20 bn for metro lines within next 4 years.

Map: Onur Uysal

Related Articles:
Best Rail Solutions in Turkish Cities
Public Transport by Rail in Turkish Cities
Urban Transport by Rail in Istanbul

2 thoughts on “13 New Metro Lines for Istanbul

  1. That’s not really clear. Is Yenikapı-İncirli going to extend M2 or the Beylikdüzü line in the end ?
    The 2 Sultanbeyli / Yenidoğan lines are going to be 2 branches of M5 ?
    And how about this Kafkaian situation around Kaynarca :
    Since municipality released maps showing Kartal-Kaynarca-Havalimanı as an extension of M4, it seemed clear that it would simply replace the eventual metro line between Pendik and airport. Yet, Mr: Topbaş announced the work on this Pendik Kaynarca line to start next year. What does it mean? How is it going to be integrated with the metro network? Is it going to be a 2 stations short connexion or a real metro line?
    I presume that Kaynarca-Tuzla and Kaynarca-havalimanı are going to be 2 branches of M4?
    Thanks for your answer.
    Robin

  2. Well, none of the questions about being branch/extension/connection, is clear in the announcements. Kartal-Kaynarca will surely be an extension, it’s seen on rail cars, but for rest I think we have to wait..

Leave Your Question/Comment

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s