The scope, rotue, stops and history of Bursa-Osmaneli high speed train line which is under construction:
Below post was prepared in 2018. Please check our new article about up-to-date and detailed information about Konya Karaman high speed line.
Project overview
- Owner: Turkish State Railways
- Phases:
- Construction of double-lane railway for a speed of 200 km/h
- Signalization and electrification
- Contractor:
- Infrastructure/tracks: Kolin-Gülermak
- Signalization: Yapı Merkezi–Elsitel
- Electrification: Yapı Merkezi
- Contract date: Infrastructure/tracks: 1/2014
- Contract duration: Infrastructure/tracks: 16 months
- Contract deadline: Infrastructure/tracks: 5/2015
- Contract value:
- Infrastructure/tracks: TL 235 mn
- Signalization: € 68 mn
- Electrification: TL 56.5 mn
- Commission date: Infrastructure/tracks: 1/2017
Route

Stops/connections
Konya (connection to Istanbul-Konya and Ankara-Konya HSTs) – Karaman
Trains
Project details
The current single-lane conventional line will be upgraded to high speed (200 km/h), signalized and electrified double-lane line. All level crossing will be eliminated.
- Line length: 102 km
- Travel time: Konya-Karaman: 40 Ankara-Karaman: 130 min
Cover photo: TCDD ©