Network statement soon coming
The first network statement prepared by TCDD is announced to be published by the end of this month.
The first network statement prepared by TCDD is announced to be published by the end of this month.
The tram and metro companies are being forced for change with the “local production” terms in almost all of the recent tenders.
Izban started direct services between Aliaga-Cumaovasi and Menemen-Tepeköy.
Construction works at Marmaray, which almost stopped for last 2 years, had restarted, but is progressing very slowly.
Istanbul Metro started survey about “woman-only-cars”.
There left only one step before foundation of new train operator company, TCDD Tasimacilik AS.
Halkali, Turkey’s most important export customs, has started to serve only trains. The new address for trucks is now Catalca.
Railway keeps an important space in investments of 2016.
İsa Apaydin is assigned as the new general manager of TCDD.
Although railway projects had a fund of TL 7bn this year, many projects will not be able to be commissioned this year. Here are the projects that will progress this year, but not be commissioned.
The timetable of high speed trains will change tomorrow.
This year, TL 7 bn is allocated for railway investments. There are many railway projects in the investment program, and 5 of them is/will be commissioned this year:
Marmaray project, which stopped for 2 years, seems to progress fast this year. Transport Ministry allocates TL 1.4bn (€ 0.4bn) for the project.
TCDD slows down in construction of high speed lines after starting many of them at the same time.
TCDD will invest about TL 600mn for passenger train sets, locos and freight wagons this year.